Skip to content

Schedule & Projects

Project Schedule

August 2021 Earthquake Schedule

(Click schedule to enlarge)

Newsletters

Emergency Repair Projects Completed

  • 22 FHWA projects and 5 FEMA projects have been completed
  • 5 construction projects were able to include earthquake repairs
  • Notable emergency projects include:
    • Minnesota Drive SE Off Ramp
    • Seward Hwy 36th to Tudor
    • Vine Rd MP 2.5
    • Glenn Parks Interchange
    • Glenn Hwy at Mirror Lake
    • Seward Hwy MP 50
    • Emergency Embankment & Drainage Repairs

FEMA Permanent Repair Project Groupings

  • Willow-Fishhook Road 
  • Knik River Road, Palmer
  • Clark-Wolverine Road 
  • Buffalo Mine Road
  • Old Rabbit Creek Road
  • Clark-Wolverine Road and Huntley Road

FHWA Permanent Repair Project Groupings

  • Glenn Highway at Mirror Lake
  • Glenn Highway MP 40-68
  • Glenn Parks Interchange Repairs
  • Central Region Bridges
  • Anchorage District Group A
  • Kenai Peninsula Area Repairs
  • Mat-Su Area Repairs
  • Anchorage District Group B
  • Mat-Su Borough Road Repairs
  • Eagle River Loop Pedestrian Undercrossing
  • Mat-Su Area Repairs – Group B
  • Dowling and 3rd Ave Repairs
  • Briggs Bridge Repairs
  • Eagle River Loop Stormdrain
  • Road Weather Information System